E.S. Boulos Co. completes CMP substation project

February 02, 2012 - Northern New England
E.S. Boulos Co. has completed the $1.8 million CMP substation upgrade project that entailed change outs, line terminal upgrades, and P&C system modifications at 12 existing brownfield substations. Construction began in late summer 2011 and was completed in December. ESB's project manager was Tom Rousseau.

New England Real Estate Journal • 17 Accord Park Drive #207, Norwell MA 02061 • (781) 878-4540 • Contact