2026 Industrial Review Spotlight - Featured Project: Plumbers’ Supply Co. Lynn

July 31, 2026 - Spotlight Content

Lynn, MA As Plumbers’ Supply Co. continues to invest in its growing operations across Massachusetts, the company has once again partnered with CM&B to deliver a new branch location in Lynn. The project represents the next chapter in a long-standing relationship built on trust, collaboration, and successful project delivery. 

Following the demolition of an existing warehouse on the site, construction is underway on a new 30,000 s/f building with a 10,000 s/f mezzanine. Designed to support Plumbers’ Supply’s growing operational needs, the ground-up facility will serve as the company’s new Lynn branch location, providing expanded warehouse, retail, and distribution capabilities upon completion this winter.

The project builds on a relationship that began in 2019 when CM&B partnered with Plumbers’ Supply to deliver its 192,000 s/f Corporate headquarters and distribution center in New Bedford. The decision to work together again reflects the strength of that partnership and a shared commitment to supporting the company’s continued growth. 

Designed by RKB Architects, Inc., with structural engineering by Flood Consulting and MEP/FP engineering by Building Engineering Resources, the project team is collaborating to deliver a modern industrial facility tailored to Plumbers’ Supply’s current and future operational needs. 

For Plumbers’ Supply, the new Lynn branch represents another investment in its employees, customers, and communities. For CM&B, it is an opportunity to continue building alongside a valued repeat client, delivering a facility that will support the company’s next phase of growth throughout the region.

Project Information:

  • Project Title: Plumbers’ Supply Co. Lynn Branch Redevelopment
  • Project Location: Lynn, MA
  • Project Type: Industrial / Warehouse / Retail Distribution
  • Building Size: 30,000 s/f warehouse with 10,000 s/f mezzanine
  • Construction Type: Ground-up
  • Scope: Demolition of an existing warehouse and construction of a new retail, warehouse, and distribution facility
  • Status: Under Construction
  • Estimated Completion: December 2026

Project Team:

  • Owner: Plumbers’ Supply Co.
  • Construction Manager: CM&B
  • Architect: RKB Architects, Inc.
  • Structural Engineer: Flood Consulting
  • MEP/FP Engineer: Building Engineering Resources (BER)