News: Construction Design & Engineering

General contractor’s false certifications bar it from any recovery from owner - by Maury Lederman and Sara Bryant

In a case of first impression, a Mass. Superior Court judge recently ruled that a general contractor, G4S (the general), could not recover any of its over $14 million claim against a public owner MTPC (the owner) because it had violated its contract with the owner by certifying that it had paid its subcontractors in full and on time when in fact it hadn’t. This harsh result should serve as a warning to general contractors and others to take seriously their contract requirements, including the certifications they routinely sign as a part of the payment application process.

Maury Lederman Maury Lederman, Murtha Cullina

The general contract required the general to pay its subcontractors all sums due within the time required by the subcontracts, and to certify that it had done so in its payment applications to the owner. The general submitted dozens of such certifications to the owner knowing full well that it hadn’t paid its subcontractors as required. The general utilized the sums paid by the owner but not to paid to its subcontractors to make its financial condition look better to outsiders, e.g. shareholders or potential investors. The owner paid the general in reliance on the false certifications. The general eventually paid its subcontractors all sums due.

The owner refused to pay the general a $4.1 million contract balance or $10.1 millioin in extra work claims citing the general’s intentional failure to pay its subcontractors as required. The general then sued the owner claiming that it would be unfair for it not to pay over $14 million because its subcontractors had suffered relatively little harm, in comparison to the $14 million claim.

Sara Bryant, Murtha Cullina Sara Bryant, Murtha Cullina

The court found that neither the fact that the general eventually paid its subcontractors all sums due, or the fact that the late payments to the subcontractors did not adversely affect the project or harm the owner in any material way, changed the fact that the general submitted false certifications to the owner to induce it to pay the general. The judge dismissed the general’s suit because filing the false certification was an intentional breach of the contract. The court applied long-standing Mass.decisional law that a contractor which intentionally violates a contractual requirement cannot recover anything for its work, except in the case of “de minimus” departures or where there are other mitigating factors, e.g. the owner was partially responsible for the contractor’s failure to perform. Finding that the false certifications were not “de minimus”, that there were no mitigating factors, and that the general, by definition, did not endeavor to perform fully its contract obligations in good faith since it intentionally ignored those obligations, the court dismissed the general’s suit against the owner.

The court justified the harsh result here in part on the fact that some of the funds the owner used to pay the general were from a Federal grant, the purpose of which was to benefit subcontractors hurt by the 2008 financial crisis. Also, the fact that the general furnished numerous knowingly false certifications for a period of more than a year likely also contributed to the judge’s willingness to impose such a harsh result.

This decision is yet another reason why contractors and their employees must be careful in certifying that its subcontractors have been paid in order to get paid. Although the court did not find that the general’s certifications were fraudulent, a person who signs false certifications stating that subcontractors were paid could also be personally liable for the owner’s loss, i.e. the signer is not protected by the corporate “veil.”

Maury Lederman and Sara Bryant  are partners and members of the construction law and litigation department at Murtha Cullina, Boston.

MORE FROM Construction Design & Engineering

Timberline Construction Corp. completes renovations for Neurology and Infusion Center of New England

Foxborough, MA Timberline Construction Corp. (Timberline) has completed a 20,000 s/f healthcare construction project for the Neurology and Infusion Center of New England at 18 Washington St. The full interior renovation transforms an existing two-story medical office building into a purpose-built outpatient care environment that doubles the center’s clinical footprint, expands services and positions the growing practice for its next chapter.
READ ON THE GO
DIGITAL EDITIONS
Subscribe
Columns and Thought Leadership
Greenwood Credit Union City Hall Plaza nears completion - by Frank Picozzi

Greenwood Credit Union City Hall Plaza nears completion - by Frank Picozzi

After several years of planning, construction, and anticipation, the community is eagerly awaiting the opening of the Greenwood Credit Union City Hall Plaza and outdoor skating rink later this month.
ABC-Mass. chairman’s message:  Rent control isn’t the answer to our housing crisis - by Luiza Mills

ABC-Mass. chairman’s message: Rent control isn’t the answer to our housing crisis - by Luiza Mills

As you may know, Massachusetts voters will be weighing in on a number of ballot initiatives in November. Among them is a proposal to impose the nation’s strictest statewide rent control policy. I’d like to tell you why the ABC MA Board
It’s time to lead: Confronting mental health in construction - by David Watts

It’s time to lead: Confronting mental health in construction - by David Watts

As we close Mental Health Awareness Month, we must be clear: May isn’t just about ribbons, hashtags, or lunchtime mindfulness apps. It’s about responsibility to confront hard truths that linger in silence, and to challenge ourselves, as leaders in our industry, to do more.
Navigating tariffs and material  uncertainty in today’s construction market - by Karl Ginand and Tiffany Gallo

Navigating tariffs and material uncertainty in today’s construction market - by Karl Ginand and Tiffany Gallo

As headlines around tariffs seem to dominate the news daily, many considering construction projects have anticipated major cost escalations and widespread supply issues. While tariffs haven’t driven pricing spikes to the extent once feared, the lasting impact has been a new layer of uncertainty, affecting more than just budgets.