Shawmut Design and Construction $550 million renovation of Boston University’s Warren Towers shifts to new phase with start of school year

Boston, MA The $550 million renovation of Boston University’s Warren Towers—the nation’s second-largest non-military dormitory—is entering a new phase as students return to campus for the start of the school year. Shawmut Design and Construction, a $2 billion national construction management firm, is leading the multi-year modernization project in partnership with architect Miller Dyer Spears and Owner’s Project Manager LeftField Project Management. The renovation spans all three 18-story towers and is scheduled for completion in summer 2028.

To minimize disruption, Shawmut is implementing a phased plan under which two towers remain occupied while one tower at a time is closed for renovation. Tower A is currently offline through summer 2026, with Tower B and Tower C scheduled for successive renovations in 2026–2027 and 2027–2028, respectively. Several measures are in place to minimize disruption to students, including scaffolding, protective wrap, and a Personnel and Material Hoist (PMH), which enable exterior masonry repairs and window replacement to proceed year-round while safeguarding the campus community from dust and debris.

Warren Towers is one of the most visible dormitories in the U.S., located on Boston’s busy Commonwealth Avenue alongside the MBTA Green Line near Kenmore Square, Fenway Park, and Back Bay. Built in the 1960s, the traditional-style residence has long been home to 1,800 undergraduate students.

“As a firm rooted in Boston and trusted to deliver complex projects on active urban campuses, we are proud to partner with BU to bring this legendary residence hall into the 21st century,” said Kevin Sullivan, executive vice president of Shawmut Design and Construction’s New England region. “With safety for students, staff, and the community guiding every step of the process, we’re excited to deliver modern, comfortable, and sustainable spaces that will support student success for years to come.”

The first phase, focused on Tower A and the adjacent dining hall, includes complete remodeling of student rooms and lounges with new walls, floors, ceilings, doors, lighting, and electrical devices. Each residence room will feature air conditioning, while corridors and common spaces will receive new finishes and lighting. Existing bathrooms are being replaced with private, accessible, all-gender facilities. Additional upgrades include new plumbing, IT infrastructure, and security systems, as well as a fully renovated dining hall outfitted with new cooking equipment, furniture, and serveries.

The building exterior is undergoing full masonry repair and restoration, with all windows being replaced and insulation added to exterior walls and roof areas to meet current energy codes. Roof systems, including drainage, are also being replaced to ensure long-term performance.

Each residential tower will be offline for approximately 15 months before reopening in time for the following fall semester. With Tower A closed, the university has arranged housing for 595 first-year students at its Fenway Campus.

The Warren Towers renovation is registered with a goal of LEED Gold certification and aligns with Boston University’s Climate Action Plan. Once completed, the project will contribute to the university’s net-zero greenhouse gas emissions goal through electrification of heating systems and the use of clean energy offsets.

READ ON THE GO
DIGITAL EDITIONS
Subscribe
Columns and Thought Leadership
Florida ruling raises bar for condo terminations and buyouts - by Michael Karsch

Florida ruling raises bar for condo terminations and buyouts - by Michael Karsch

On October 14, 2025, in a landmark decision with significant implications for the Florida real estate market, the Supreme Court of Florida formally denied Two Roads Development’s (TRD Biscayne LLC) petition for review in its long-running case against unit owners of Biscayne 21,
IREM president’s message:  Our new reality - Staying ahead of supply chain delays - by Yoany Vargas

IREM president’s message: Our new reality - Staying ahead of supply chain delays - by Yoany Vargas

Supply chain delays are slowing construction, ratcheting up operating costs, and extending turnover timelines across Greater Boston, directly reducing revenue and increasing the workload for multifamily and

Revitalized Town Centers:  Retail??? - by Carol Todreas

Revitalized Town Centers: Retail??? - by Carol Todreas

It is now widely accepted that customers want to shop in person at physical stores. Brands know that they do better business in a physical store than just on line so they want to open stores. Demand for retail space by digital merchants, local entrepreneurs, and newly developed national chains
Retail infill strategy to activate Pawtucket’s Conant Thread District - by Gaetan Kashala

Retail infill strategy to activate Pawtucket’s Conant Thread District - by Gaetan Kashala

Until recently, the Conant Thread District consisted of approximately 150 acres of underutilized industrial land spanning Pawtucket and Central Falls. Today, the area is one of the most significant